Caustic Sedimentation Tank Installation and Integration

We successfully completed a groundbreaking project to optimize caustic recovery for one of our clients. This custom-engineered solution addressed a constraint that they had with caustic sedimentation only possible on one of their five packaging lines.

Our team designed and integrated an new Caustic Sedimentation Tank. By increasing settling time from 8 hours to 24-48 hours, we achieved optimal caustic recovery while maintaining uninterrupted production.

To ensure continuous operation, we implemented advanced automation features that enabled a duty standby system. This innovative approach guaranteed maximum uptime and efficiency.

Our solution combined engineering expertise with a deep understanding of the caustic recovery process to deliver tangible results:

  • Enhanced caustic recovery
  • Improved product quality
  • Increased production efficiency
  • Reduced downtime


This project is a testament to our ability to provide cutting-edge solutions that drive operational excellence.

Client

Confidential

Location

South Africa

Services

Process-, Civil-,Utilities Engineering and Project Management

Project Duration

4 Months